Media/Elwyn Regional Rail Line Crum Creek Viaduct (M.P 11.87)

Update: The contractor continues landscaping and site restoration activities, including access road removal. Work is anticipated to be complete by mid-November 2016.

Work will replace this 925-foot-long, 100-foot-high bridge, which was originally constructed in 1895 and repaired in 1983.