Delaware County
Engineering/Design Firm: HNTB
Clean and paint the steel catenary structures that support the overhead traction power contact system. The work will also include miscellaneous steel repairs. These poles have not been painted since they were installed in the early 80's.
General Contractor | Buttonwood Company, Inc. (DBE Primary Contractor)
$537,500
Change order for West Chester Yard Pole Painting and Anti-Gravity Coating of 40 Foundations on Routes 101 & 102 started on September 01, 2010.
Change order was completed on September 13, 2010.
Pole Painting passed Adhesion Test.
All Primer Coat Work is complete.
Project was completed on August 26, 2010.
Buttonwood is approximately 68% completed with physical construction.
Coordination with PECO for power outages on their aerial attachments on certain of our structures has been impacted by the storm of June 24th.
Outage #4, for the entire Media-Sharon Hill Line, started.