Delaware County
Engineering/Design Firm: SEPTA
Replace rail, dating back to 1922, with new Continuous Welded Rail (CWR) and Pandrol fixation.
Work will also include brush cutting.
General Contractor | Railroad Construction Company (Rail Installation)
$8,284,895
General Contractor | K.W. Reese (Brush Cutting)
$977,730
Second Brush Cutting Contract is instated to perform trimming that was not originally slated to be done in initial contract.
All trimming assigned by Second Brush Cutting Contract is complete.
Brush Cutting Contract #1 is complete.
RCC began flash butt welding at Bywood Station during the week of June 14th and has completed all the new rail strings for the Trunk Line.
All 230 Trees that were marked as Dead and Danger Trees (DDT) have been removed.
K. W. Reese remobilized on June 14th at the start of Outage #4, and the work is substantially completed.